Kasson City discusses utility territory acquisition and potential substation near Public Works
Summary
City leaders discussed confidential negotiations with Peoples over utility service territory, noted Peoples CEO Mike Hinkie's upcoming retirement and an ExCel study that showed capacity to serve up to 27 MW; staff outlined a likely substation site near Public Works and said a closed session may be needed before finalizing terms.
Get email alerts on the Utilities topic
No spam. Unsubscribe anytime.
City Administrator updated the council on negotiations to expand Kasson Public Utilities’ service territory and on studies for a local substation.
Administrator said the council's goal is for Kasson Public Utilities to serve all Kasson City residents and confirmed staff have been negotiating with Peoples; details of the negotiations were described as a trade secret and staff told council members that a closed session is likely at the next meeting so members can review confidential terms. Administrator also noted Peoples CEO Mike Hinkie is retiring at year end and has asked the city to finalize discussions before he leaves.
On infrastructure, the Administrator summarized results of an ExCel study that found the local system could support up to about 27 megawatts of load with transmission. Staff said the next step is a facility study to estimate costs for tying into the regional grid and that a probable substation site would sit near the Public Works facility on the north side of 16th Street, chosen to reduce nearby residential impact and because the city already controls the site.
What's next: Staff indicated no rate increases are currently required for projects already approved and that the facility study would generate cost estimates and more definitive siting information. Council was told to expect more discussion, including a potential closed session, at the next meeting.
Quote
City Administrator (paraphrased): the council aims for Kasson Public Utilities to serve all Kasson City residents and negotiations with Peoples are ongoing; staff described the negotiation details as confidential and flagged a closed session at the next meeting.
Closing
Staff will bring back the facility study results and additional negotiation details (in closed session if necessary) at a subsequent council meeting.