Highway superintendent reports 281.8 miles graded; crusher and scraper under repair

Dawes County Board of Commissioners · June 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Highway Superintendent Wade Yada told the Dawes County Board crews graded 281.8 miles across three districts over two weeks and reported a belt splice repair on the crusher and ongoing scraper repairs; next pit move planned to Goff.

At the June 24 meeting of the Dawes County Board of Commissioners, Highway Superintendent Wade Yada reported county road crews graded a combined 281.8 miles over the past two weeks and outlined ongoing equipment repairs.

Yada said District 1 finished rocking Davenport Road and will next blade McHenry Road, District 2 is blading roads where washouts occurred, and District 3 is patching bad spots. He provided district totals: District 1 — 82.5 miles, District 2 — 99.8 miles, District 3 — 99.5 miles.

Yada also reported a splice in the crusher belt was coming apart and is being repaired; the crusher will then move to the Goff pit. The county’s scraper remains under repair. No formal board action was taken; the report was informational.