Council hears timeline for marina rebuild, dry storage opening and mooring-field repairs
Summary
City staff told council the new South Complex dry-storage facility is on track for a mid-March completion, with plans to phase boats in and begin revenue by May 1; mooring-field repairs aim for September 2026 and the main marina rebuild could require a temporary shutdown in March 2028.
Speaker 4 said the South Complex dry-storage facility is nearing completion and staff are targeting March 15 for substantial completion, with final finishing work and landscaping to follow. "They are on track for that," he said, adding that racking and electrical hookups are being installed and roll-up doors and a power meter are already in place.
The project team plans a phased move-in of boats once the certificate of occupancy is received; staff aim to have the facility filled and producing revenue by May 1 to…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat