Moreland Elementary renovation: Act 34 hearing scheduled May 21; project capped at $15.5M
Summary
Consultant Crabtree presented Moreland site and floor plans showing a new cafeteria, classroom addition to remove modulars, reworked parent/bus circulation, new playgrounds and a pedestrian‑friendly layout; the board was asked to pass an Act 34 resolution at its next meeting to authorize a May 21 public hearing and a maximum construction cost of $8.2M (total project $15.5M).
Get email alerts on the Facility Upgrade topic
No spam. Unsubscribe anytime.
Crabtree, Waubon & Associates presented site and floor plans for the Moreland Elementary renovation and addition. The plan would add a new cafeteria and kitchen, create a classroom addition that would allow removal of existing modular classrooms, provide an internal courtyard and outdoor learning spaces, and reconfigure traffic flow so bus drop‑off and parent drop‑off are fully separated. Consultants emphasized preserving a nearby recreational space and adding pedestrian connections and bike parking.
Crabtree explained Act 34 requirements (the state law governing public hearings for school construction or increases of more than 20% of building area) and said the district must advertise the public hearing and notify residents within 200 feet. The consultant presented an Act 34 maximum building construction cost of $8.2 million (addition/construction only) and listed other project costs (soft costs, contingencies, financing) that bring the maximum project cost to approximately $15.5 million. The Act 34 public hearing is scheduled for May 21 at 5 p.m. at Moreland Elementary; the board will consider the resolution that authorizes the hearing at its April 23 meeting.