Chickasaw County clears 2-megawatt Dairyland Power solar array and battery storage
Loading...
Summary
The Chickasaw County Board of Supervisors unanimously approved Resolution 04-13-26-26 on April 13 to allow Dairyland Power Cooperative to construct a 2-megawatt solar array with battery storage in NE¼ of Section 11 (Township 95N, Range 12W).
Dairyland Power Cooperative presented a plan to construct a 2-megawatt solar array and associated battery storage facility to be located in the NE¼ of Section 11, Township 95 North, Range 12 West in Chickasaw County. The county land use administrator recommended approval of the project plan.
Supervisor Cerwinske moved and Supervisor Breitbach seconded a resolution (04-13-26-26) approving the proposed solar array and battery storage facility. The minutes record the vote as Ayes: Cerwinske, Breitbach, Carter, Suckow, Hackman; the resolution was passed and the chair was directed to certify the approval. The minutes refer readers to the auditor's office and the county website for detailed documentation.
The approval authorizes Dairyland Power to proceed on the proposed location described in the resolution. The minutes do not record additional conditions or permit details beyond the land use administrator's recommendation; detailed permitting and site documents are on file with the auditor's office.