Committee awards industrial-streets contracts but notes budget delta; bond issuance required

West Chicago Infrastructure Committee · February 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Infrastructure Committee approved awards for Penn Lane and Downs/Western Drive reconstruction but staff warned the Downs/Western bid (~$7.64M) exceeds the $6.1M budget by roughly $1.5M; both awards are contingent on general-obligation bond issuance and will appear on a March 2 agenda for bond approval.

The committee voted Feb. 5 to move forward on industrial-streets improvements, including Penn Lane reconstruction and a larger Downs Drive/Western Drive project, while noting a substantial budget gap for the latter.

Staff described a multi-year industrial-streets program (2026–2028). Penn Lane is slated for reconstruction without underground water-main replacement; Downs Drive and Western Drive include underground water-main replacement and required roadway widening to meet industrial standards, which added cost. Staff said Downs Drive requires widening by about 8 feet across roughly 2,500 linear feet, increasing the project area by nearly 20,000 square feet and contributing to higher costs.

Bids were competitive; the low bid for the Downs/Western project came in at about $7.64 million against a $6.1 million budget, creating an approximate $1.5 million delta. Staff told the committee they expect to fund both projects with general-obligation bonds and that awards are contingent on successful bond issuance; accordingly, the items will be scheduled for the March 2 agenda following the planned bond issuance action.

Staff also outlined the city’s three-year capital plan and said a $3 million grant expected in 2027 could reduce total debt issuance for the 2026–2028 program from an earlier $22 million projection to around $19.8 million. Committee members asked about drainage at a flooding-prone section and staff said drainage improvements and strategically placed inlet structures are included in the reconstruction design.

The committee approved awards for the projects with the condition that bond issuance occur; staff will coordinate bond timing and final contract awards once the financing is secured.