Chase City Elementary update: asbestos found under slab; permit expected, completion targeted 2027
Summary
Project manager Dalton told the board abatement and demolition are complete, additional asbestos was discovered under the slab and is scheduled for removal this week, permit drawings were submitted with a building permit expected by week’s end, and the project’s substantial and final completion dates are currently projected as 04/08/2027 and 06/15/2027.
The board received a construction update on the Chase City Elementary School project from Mr. Dalton, who reported steady progress despite recent weather delays.
Dalton said crews have completed installing water lines and a temporary office, are using the existing gym as a temporary office space, and have finished abatement and demolition of the old building. "We…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat