Board hears design update and phased timeline for North Stafford High School fine‑arts wing

Stafford County Public Schools · April 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facilities staff outlined a phased renovation and a ~6,000 sq ft band and orchestra addition for North Stafford High School, described acoustic mitigation measures, and gave a summer bidding timeline with construction planned to limit impact to in‑school operations.

Jason, the division's chief facilities officer, presented a design and permitting update for the North Stafford High School fine‑arts wing and an adjacent band and orchestra addition.

Jason said the project is currently in design and permitting and that the team "anticipate[s] that we'll begin the bidding in on or about June" with a one‑month bid window and contract approval in August–September if schedules hold. He described a phased approach: phase 1 builds the new orchestra and band room and associated practice rooms and instrument storage; phase 2 will include lighter auditorium renovations during the summer; the heavier backstage renovation would follow and is expected to take place during the subsequent school year.

On acoustics and adjacency to the library, Jason and the construction director (introduced by Jason as John Kramer) said they chose the location to meet the footprint and acoustic goals. An acoustic specialist is working on material and ceiling‑height solutions; Kramer and the architect team said they will use higher ceiling heights, acoustic matting and treatment panels, and a hallway buffer to reduce sound transfer.

Jason said the addition is outside most of the existing footprint so much of that work can occur with minimal interior disruption; however, some temporary reassignments of drama/choral space are expected during the heavy renovation. He estimated that, if everything moves according to plan, the project could be completed by early 2028, but cautioned dates may shift based on permitting and final contract timing.

Board members asked about noise transfer to the library, temporary space for classes during construction and the total estimated cost; staff said they will provide updated cost numbers and refined timeline details in forthcoming memos.

No formal action was taken; staff offered to share the presentation and cost estimates with the full board and to provide additional details for upcoming budget and joint‑work sessions.