Greenskies agrees to larger inverter setback, will provide visual simulation for Scotland solar project
Loading...
Summary
Greenskies told the Scotland Board of Selectmen it will increase the inverter setback from 215 to 449 feet, produce a visual simulation for nearby view from Gager Hill Road, and said its liability insurance would cover third-party damage though abutters are not typically added as additional insured.
Representatives of Greenskies updated the Scotland Board of Selectmen on a proposed solar project on April 23, saying the company has agreed to increase the inverter distance from neighbors’ property lines and will provide visual materials for public review.
A Greenskies representative said the inverter setback will be doubled from 215 feet to 449 feet to reduce disturbance to nearby livestock. The company expects to deliver a visual simulation of the project view from Gager Hill Road, showing vegetative screening and agricultural-style fencing, in about one month.
On insurance and abutter protections, the Greenskies representative told the board that the company’s liability insurance would cover third-party property damage in events such as panels detaching, but that it does not typically add adjoining homeowners as additional insured; usually only parties with a direct interest in the facility (landlords, contractors, financiers) are named. The company declined to discuss a local tax-stabilization agreement pending resolution of a proposed state-mandated payment calculation described in the meeting as $12,000 per megawatt with a 2% annual rise until the project goes offline.
What happens next: Greenskies will work with individual neighbors and produce a public visual simulation to be provided for reference once complete.