City gets progress update on 10th Street, Beach Street and roundabout projects; 10th Street work suspended until next season

Brainerd City Public Works / Council Committee · October 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public works staff reported several schedule changes: 10th Street reconstruction is behind and suspended until next year; Beach Street paving and Wright Street undergrounds have revised October targets; the roundabout project is nearing completion and expected to open in late October.

Public works staff gave the committee a construction update across multiple projects.

Staff said the 10th Street reconstruction is behind schedule and that work on that corridor will be suspended until the next construction season. On Wright Street, underground work for a segment is expected to be completed in mid‑October with curb/gutter and first pavement lift to follow. Beach Street south section work was completed; the north section curb and first lift paving were targeted in mid‑October. The roundabout project was reported to be on schedule for final payments and striping in mid‑ to late October with an anticipated opening thereafter.

Staff said if projects miss completion deadlines they will prepare options for council, including possible contract suspension or termination.