Committee approves city share of Country Manor utility change order

Brainerd City Public Works / Council Committee · October 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Brainerd City staff brought a reduced change‑order cost for Country Manor utility work; the committee approved splitting the $42,311 request roughly 50/50 with BPU (city share $26,155.50) with the city portion to come from the general fund.

The committee approved a staff recommendation to share the cost of a change order needed to extend utilities for Country Manor.

Public works director Abigors told the committee the contractor’s final cost for the utility extension was $44,850; Country Manor absorbed a 6% overhead adjustment, reducing the city’s request to $42,311. Abigors said the utility commission recommended splitting the remaining cost roughly evenly: the city would pay $26,155.50 and BPU would cover $16,155.50. Staff noted the city portion would come from the general fund.

Council members asked why the expense was not charged to a sanitary sewer line fund; staff replied that fund balances were low. After discussion about record checks and the sequence of surveying versus digging, a motion to approve the 50/50 split passed by voice vote.

The committee instructed staff to continue vetting any related change orders and to report back if additional recovery options or contract clarifications are identified.