Livingston council approves $63,616 change order for South Washington water line project

City Council of the City of Livingston, Texas · October 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved Change Order No. 1 for the South Washington Water Line Improvement Project to cover additional right‑of‑way clearing and select backfill, increasing the project cost by $63,616, payable from local funds.

Engineer Dalton Brown of The Brannon Corporation presented Change Order No. 1 to the council, explaining the need for additional right‑of‑way clearing and the use of select backfill for pipe bedding that produced a cumulative overrun. The change order totaled $63,616.00 and was presented for payment from local funds.

Alderman Alan Cook moved approval of Change Order No. 1; Alderman Andy Evans seconded. The motion passed with all present voting aye. City staff did not present a further breakdown of the cumulative overrun at the meeting.

The council’s approval authorizes the contractor to proceed under the adjusted contract terms; staff indicated the funds will come from local budgeted resources.