Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Council Votes topic
No spam. Unsubscribe anytime.
Votes at a glance: council adopts ordinance on gas right-of-entry, approves Boise Creek Cove final plat and passes planning work plan amendments
Summary
At its March 9 meeting the council adopted Ordinance No. 2835 (right-of-entry for gas inspections), approved Resolution No. 1869 accepting the Boise Creek Cove final plat (18 lots), adopted Resolution No. 1870 (local road safety plan) and approved the 2026 Planning Commission work plan as amended, including an authorization of up to $25,000 for outside Title 15 consultant work.
Get email alerts on the Council Votes topic
No spam. Unsubscribe anytime.
The Uniontown City Council took multiple formal actions on March 9, adopting an ordinance and several resolutions and approving planning work items.
Ordinance 2835 (adopted): The city clerk read Ordinance No. 2835, which amends the municipal code to authorize city employee access to buildings where natural gas is supplied to permit inspections and provides remedies if an inspection is not allowed. Staff recommended approval and the council voted to adopt the ordinance by voice vote.
Resolution 1869 — Boise Creek Cove final plat (approved): Director of Planning Chris Besany recommended approval of Resolution No. 1869 to accept the Boise Creek Cove final plat, an 18‑lot subdivision on just under 10 acres in the R‑2 (moderate‑density single‑family) zone. Besany said required infrastructure, posted bonds and required certifications were in place; council approved the resolution by voice vote.
Resolution 1870 — Local Road Safety Plan (approved): Council adopted Resolution No. 1870 to adopt the local road safety plan, which identifies nine candidate areas and roughly $21,000,000 in potential improvements. (See separate coverage of public comment and next steps on the Stevenson & Cole intersection.)
Planning work plan and consultant authorization (approved): The council considered the 2026 Planning Commission and Community Development work plan, approved an amendment removing the building-height review for the R4 and HCB zones from the docket, then voted to approve the work plan as amended. The council then authorized administration to spend up to $25,000 for outside contractor/consultant work to revise Title 15 amendments needed to comply with state law.
Votes and procedure: All actions reported at the meeting were approved by voice vote; the clerk and staff provided the ordinance/resolution texts and staff reports prior to each vote.
Why it matters: The ordinance clarifies inspection authority related to natural-gas service, the Boise Creek Cove approval advances an 18-lot subdivision toward build-out, and the planning work plan and consultant authorization enable the city to proceed with code updates required by state law.