Staff update: Brownfield study, taxiway D rehab (~$5M), PAPI award and maintenance work at Kingman Airfield
Loading...
Summary
Staff reported progress on multiple airport and industrial-park projects, including a received Phase I Brownfield environmental report for a former dump site and a taxiway D rehabilitation design at roughly 75% with a project cost estimated around $5,000,000; staff also described PAPI contract award, navaid lighting design, apron maintenance, hangar wait-lists, and a short-term projected deficit.
A staff member presented an extensive update on airport and industrial-park work, detailing completed, in-progress and proposed projects and noting funding dependencies on ADOT and FAA.
Key project updates included: a near-complete paving of Government Way and Transport Way that will be turned over to county maintenance after punch-list items; receipt of a Route 66 Brownfield Coalition Phase I environmental report for a former county dump site adjacent to BLM-leased property and pursuit of a Phase II (soil/air sampling and modeling) to determine buildability; and taxiway D rehabilitation and design that staff said is about 75% complete and would cost "around $5,000,000." Staff said they are pursuing FAA discretionary funds and may phase funding if full federal support is not available.
On procurement and construction: staff said the notice of award for the PAPI project was sent to Mesquite Electric as the lowest bidder and that the contract will proceed once bonding and insurance are finalized. For navaid lighting and sign design, staff reported receiving ADOT grant funding for design work and shifting certain lighting work into the Delta reconstruction project to reduce scope for separate projects.
Maintenance and operations: staff described ramp and parking-lot saw-cutting and crack repairs now under way, a plan to use silcoat to extend pavement life on T-hangars, and an anticipated completion date for current maintenance work (staff said they expected it to be complete by Friday). Staff also provided hangar occupancy and wait-list figures for several hangar groups and said airport revenue and expenses show a recent downturn; staff said the airport is expected to operate at a deficit for roughly one to two years while capital repairs and encumbrances are addressed and that reserves are expected to cover the shortfall.
Staff quoted on costs and timing included: "This project is gonna cost around $5,000,000" (taxiway D estimate) and that the PAPI contractor was the lowest bidder and is completing bonding. Commissioners asked about rate studies and staff said any rate or fee changes would be brought back through the budgeted process and would return to the commission for review if appropriate.
Next steps and funding: staff said many projects depend on FAA/ADOT decisions and that having design documents ready would help pursue additional funding when it becomes available. The commission received the report and had no formal action on these items during the meeting.