City staff announces Bradley Road bridge reaches construction milestone

Menifee City · April 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A city staff member announced that Menifee's Bradley Road Bridge project reached a key construction milestone after crews placed 863 yards of concrete; deck falsework will begin next and storm drain work is underway. The city said the roughly 365-foot bridge is designed to improve safety across Salt Creek Wash.

A city staff member announced that Menifee's Bradley Road Bridge project reached a key construction milestone this week, saying crews placed 863 yards of concrete on the bridge's stem and soffit sections.

"Great news, Menifee," the staff member said, describing the placement as a critical step for the project.

The staff member said crews will next construct the bridge deck falsework in preparation for the deck pour. Storm drain work on the south side of the project is underway and "is expected to be completed soon," the staff member added.

City officials described the structure as a roughly 365-foot, state-of-the-art bridge with structural and seismic design elements and hydraulics improvements intended to give motorists, pedestrians and first responders a safer passage across the flood-prone Salt Creek Wash. "We're excited for the conclusion of the project in the coming months," the staff member said.

The city provided a project page for further information: cityofmenifee.us/bradleybridge. No votes, motions, or formal actions were recorded in the announcement.

The immediate next construction milestone is the deck pour, which will follow completion of the falsework and associated drainage work.