Hearing officer approves Harborview Inn canopy expansion and as-built monument sign at 222 West Cabrillo Boulevard
Loading...
Summary
Assistant planner Jillian Fennessy recommended and Staff Hearing Officer Tess Harris approved a front-setback modification to allow a canopy extension and an as-built monument sign at the Harborview Inn (222 W. Cabrillo Blvd); staff conditioned archaeological monitoring due to site sensitivity.
Tess Harris, Staff Hearing Officer, approved a front-setback modification for the Harborview Inn at 222 West Cabrillo Boulevard at the April 22 meeting after a staff presentation and brief applicant comments.
Jillian Fennessy, assistant planner and case planner, told the hearing the 72,107-square-foot site is developed with a three-story hotel and a one-story restaurant. Fennessy described a proposed extension of the entry canopy that would cover the entry ramp and landing and permitting of an as-built monument sign in front of the main lobby. "The canopy will encroach approximately 9 feet and 3 inches into the setback, leaving 9 inches from the property line," Fennessy said. The record shows staff recommended approval because the addition is consistent with neighboring buildings that have permitted facades up to the property line.
Fennessy also explained the site lies within archaeological sensitivity zones and recommended conditioning any ground disturbance to include monitoring; she said those conditions are applied where subsurface resources are suspected but not confirmed. The project previously received a concept review from the Historic Landmarks Commission, which found the front-setback modification "aesthetically appropriate and supportable," according to staff.
Applicant Miles Henry said the canopy is intended to protect the terracotta tile entry ramp and landing from rain, calling the canopy necessary to prevent slippery conditions: "We're just trying to protect the the ramp and the stairs, the nice slick terracotta tile." Henry also said the applicant would adjust the monument sign to address visibility concerns raised in the staff report.
Harris made the CEQA finding that the project qualifies for an exemption under CEQA Section 15301 (existing facilities) and made the modification findings that the addition is consistent with the zone and neighboring development. She approved the project; the approval is subject to a 10-day appeal period under the permit process and staff report conditions, including the archaeological-monitoring requirement.
No public comment or written correspondence was submitted for the item during the hearing.