Lake Placid utilities to begin sewer-plant cutover this week as town aims for DEP reimbursement deadline
Summary
Town staff said the sewer plant transfer will begin Wednesday at 7 a.m.; the town aims to complete commissioning by June to secure DEP reimbursement tied to the project.
Get email alerts on the Utilities topic
No spam. Unsubscribe anytime.
Town staff reported on April 20 that the sewer-plant startup and transfer will begin Wednesday morning at 7 a.m. and that crews will work extended hours during the cutover.
The utilities lead said the work is designed to meet a June completion target so Lake Placid can secure reimbursement from the Florida Department of Environmental Protection. The mayor and council praised the progress and said they will plan a ribbon-cutting once the plant is fully operational.
Staff asked council to be available for support as needed during the cutover and said they will report back with a status update and any issues encountered during commissioning.