Council awards design and construction work for City Hall window replacement
Summary
Dalton approved a KRH Architects agreement to design first-floor window replacements at City Hall (architect fee ~6% of project, about $24,000) and awarded the construction contract to Integrated Builds LLC for $393,475; the work is funded through the city's multiyear CIP with completion targeted for 2026.
Get email alerts on the Infrastructure Maintenance topic
No spam. Unsubscribe anytime.
Dalton City Council on Monday authorized a design agreement and a construction contract to replace first-floor windows at City Hall.
The council approved a professional-services agreement with KRH Architects to produce design documents and oversee replacement details for damaged wood windows. Staff estimated architectural fees at about 6% of the completed project cost (roughly $24,000) and said the work is funded through the multiyear capital-improvement program.
Following the design authorization, the council awarded the construction contract to Integrated Builds LLC, the low bidder at $393,475. Staff said the scope covers first-floor window replacements (approximately 30–34 windows) and includes replacing rotten nailers where necessary; interior historic woodwork visible from inside the building will not be replaced. Substantial completion was listed as 2026.
Both motions passed by voice vote.
What happens next: staff will finalize the design scope with the architect and coordinate construction scheduling and CIP funding disbursement.