The committee approved a slate of procurement and public-works contracts on March 23, including sanitary sewer lining, a water-main replacement in Ward 7, a fleet equipment purchase, a DocuSign renewal, manhole rehabilitation and lighting-materials purchases; most items were routine and passed unanimously.
Get email alerts on the Votes Roundup topic
No spam. Unsubscribe anytime.
At its March 23 meeting the committee approved a series of resolutions authorizing contracts and agreements across multiple city departments. The committee recorded approvals for sewer, water, fleet, information-technology and streetlight-material procurements; most motions passed by unanimous committee vote.
Key outcomes:
- 26-0105: Fleet replacement vehicles and equipment — Approved funding of $882,628.29 to procure plows, a fork truck, trailer and a sewer truck. Chris Linville, superintendent of fleet operations, said most items are replacements; the sewer truck was identified as a new purchase. Motion passed 5–0.
- 26-0133: 2026 sanitary sewer CIPP lining project — A $1,344,479.50 contract to line selected sanitary sewer mains. Kurt Muth (Public Works) said the contract is larger this year because of increased quantity and higher prices; the city received four bids and accepted the low bidder. Motion passed 5–0.
- 26-0126: DocuSign/Carahsoft lifecycle management renewal — A one-year subscription renewal with Carahsoft/DocuSign not to exceed $101,460.20 to expand electronic signature and document-management use while the city operates a new center-of-excellence for storing signed records. Jeff Anderson, deputy CIO, described the renewal plan. Motion passed 5–0.
- 26-0147: Liberty/Catherine/Beckwith water main replacement — Awarded to Gerardi Sewer and Water Company for $1,000,849.64; scope was expanded to capture nearby piping with repeated breaks. Muth said approximately 85% of the roughly 60 services in the area are lead and that some newer services are copper; committee approved 5–0.
- 26-0152: Water main flushing consultant (CMT) — A $238,100 contract to continue a multi-year flushing program that cycles through the system in roughly four to five years; approved 5–0.
- 26-0163: Intergovernmental agreement with King County — The county will contribute $200,000 toward replacing unincorporated lead services on a block of Salafasburg; the city will front the work and be reimbursed. Motion passed 5–0.
- 26-0165: 2026 manhole rehabilitation project — $279,690 to Structured Solutions LLC for manhole repairs and lining; typical repairs take about one day per manhole. Motion passed 5–0.
- 26-0168: Streetlight fixtures and poles materials purchase — Annual solicitation awards to multiple vendors (including Graybar Electric and Dominion Lighting) to replenish inventory and address knockdowns; materials expected by late summer or early fall. Motion passed, meeting adjourned at 04:27.
Most items were described as routine maintenance or replacement work intended to preserve infrastructure and operations; committee members asked clarifying questions about funding sources, timelines and potential neighborhood impacts.