District construction update: new high school on track for fall 2027; site piping, geothermal and stadium work advancing

Westfield-Washington Schools Board of School Trustees · April 22, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Contractors and project managers told the board the new high school remains on schedule for fall 2027 with active geothermal piping, roofing, masonry and synthetic stadium field work; several projects reported contingency usage and time-sensitive sanitary sewer connections.

District construction partners gave progress reports on multiple campus projects and a timeline for openings and site work.

Mike from Hagerman Group reported exterior and interior work on the new high school, underground geothermal piping installations, roofing and masonry, synthetic stadium field preparations and that Centennial Road reconstruction work has begun. He told the board the school is scheduled to open in fall 2027 and said the sanitary sewer connection and certain land‑use elements are time-sensitive for remaining schedule milestones. "So we will be advancing onto the baseball field and the softball field, and, obviously, the school opens fall 27," he said.

Performance Services provided a progress update on Cool Creek Elementary and Westfield Middle School, including phase 2 kindergarten classroom reconfigurations, stormwater detention chamber installation to free playground space, roofing and locker-room renovation work and plans to complete many of the interior finishes during summer work windows. The firm said some work will require swing space and temporary partitions to maintain instruction while construction continues.

Representatives updating the transportation and site utilities projects reported completed sanitary and water mains, fuel-station testing, bus bay and wash-bay infrastructure work, and target move-in coordination for the transportation team. Several presentations included contingency-usage figures and described next steps for tap approvals, asphalt top-coat and site restoration.

Contractors also outlined punch-list items, interior storefront and drywall finishing, HVAC startup and playground installation schedules for Shamrock Springs and other campuses. Board members and administrators discussed coordination with the city and county on road and stormwater permitting and approvals.

Administrators asked the board for assistance in expediting a signed sewer connection document to allow final utility taps. The board heard these construction updates as part of its business and operations agenda and did not take separate votes on project scopes or change orders during the meeting.