Bolingbrook board approves $7.315 million bid for Phase IV of Water Reclamation Facility No. 3

Mayor and Board of Trustees of the Village of Bolingbrook · April 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Bolingbrook Board on March 25 approved Whittaker Construction & Excavating’s $7,315,000 bid to build Phase IV of Water Reclamation Facility No. 3; the bid is about $815,000 over budget but the project has $1.76 million in grant funding and substantial completion is expected in Fall 2026.

The Bolingbrook Village Board voted March 25 to award Phase IV construction of Water Reclamation Facility No. 3 to Whittaker Construction & Excavating, Inc., accepting the firm as the lowest responsible bidder. Trustee Jean M. Kelly moved the award and Trustee Maria A. Zarate seconded.

The village said the Whittaker bid of $7,315,000 is approximately $815,000 over the project budget. The board noted the project is receiving $1.76 million in grant funding and that Phase IV is intended to increase treatment capacity, meet acceptable effluent limits and improve process efficiency. Village staff anticipate substantial completion in Fall 2026. The item was reviewed and approved by the Public Services Committee before the vote.

The motion passed on a roll-call vote of six yeas (Carpanzano, Doris, Kelly, Lawler, Quintero, Zarate) and no nays. No public comment was recorded on the item in the meeting minutes.

The board did not provide additional detail in the minutes about how the overrun will be resolved beyond noting the grant funding; the project timeline and contract award were authorized to proceed.