Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Zoning administrator reports water project progress, new site plans and Hampstead Day plans
Summary
Town zoning administrator briefed the commission on the municipal water project (four of five mains complete; treatment plant grading imminent with construction aiming to complete four plants in mid-2027), pending site plans including a mixed-use 845 Main Street proposal, a commissioned mural by Dominic Jones, and Hampstead Day logistics on May 16.
The Hampstead zoning administrator updated the Planning and Zoning Commission on several ongoing town projects and upcoming items.
On the town water system, he said Mid Atlantic Utilities has completed four of five new mains and begun work on the last main that runs from the existing pump house toward the planned new water treatment plant on town property; grading…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat