After an architect presentation on options for a new courthouse, the board approved BVH’s project outline and timeline and voted to engage DA Davidson for legal work on bond measures to finance the project.

Chair Lisa Lunz convened the Dixon County Board of Supervisors on April 14, 2026, where architects from BVH presented building options and a proposed project timeline for a new Dixon County courthouse. The board voted to approve the outline and timeline presented by BVH.

The move advances preliminary planning for a replacement courthouse in Ponca, a step board members said is intended to clarify schedule and costs before formally seeking financing. Supervisor Neil Blohm moved to approve the outline and timeline; Supervisor Terry Nicholson seconded the motion, and the motion carried with all supervisors voting in favor.

After the presentation, representatives from DA Davidson provided information on issuing building bonds. Supervisor Steve Hassler moved to engage DA Davidson to perform legal work and advise on preparing the necessary resolutions related to bond financing; Supervisor Don Andersen seconded the motion. The board voted unanimously to retain DA Davidson for bond-related counsel.