Albertville board updates K–1 school plan and multiple facilities projects

Albertville City Board of Education · February 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Superintendent Dr. Bart Reeves told the board the district presented a capital plan to the mayor and council and provided timelines for a K–1 school, a storage building relocation, AES gym pad and AHS bleachers and video-board work.

Superintendent Dr. Bart Reeves told the Albertville City Board of Education that the district presented its capital plan to the city council and mayor on Feb. 17, outlining a vision that includes a K–1 school, a transportation and maintenance facility and other projects. Reeves said the district will hold a third meeting with the architect next week to continue finalizing the K–1 school plans.

Project updates and timelines provided by Reeves included: the storage building next to Albertville High School was nearing full disassembly and a new concrete pad was curing at the relocation site, with vertical construction expected in approximately two to three weeks; the AES elementary gym concrete pad was poured and is expected to cure in about three weeks before vertical construction; high school gym bleachers are expected to be installed beginning in June; and baseball and softball video boards are scheduled for installation by March 5.

The board received the construction and scheduling update as information; no formal contract awards, change orders or budget approvals for these projects were recorded in the meeting minutes. Reeves did not specify final project budgets, contractor names, or bid statuses during this update.