Weslaco approves $536,381 change order for airport hangar project and authorizes lease negotiations
Summary
The commission approved change order #2 for the KSA airport hangar development for $536,381 and, after executive session, authorized staff to negotiate a proposed airport lease and return with final terms.
Get email alerts on the Airport Development topic
No spam. Unsubscribe anytime.
The Weslaco City Commission on Tuesday approved a $536,381 change order for the KSA airport hangar development project and authorized staff to proceed with lease negotiations for airport property after conferring in executive session.
Staff presented change order #2 for additional services outlined in KSA's May 13, 2025 letter and recommended approval; commissioners voted to proceed. Staff noted change order #1 — for stormwater administration — is fully reimbursable through ARPA, and said the change‑order attachments were provided in the meeting materials.
After an executive session that included real‑property discussions, the city attorney confirmed the only item for action was the airport real‑property matter; the commission voted to allow staff and administration to move forward with negotiating the airport lease and to return with final details.
Mayor Adrian Gonzalez and commissioners described the airport hangar work as part of a broader effort to advance airport development and make the site shovel‑ready for tenants and operations. Staff said KSA was the original contract awardee (11/16/2023) and the change order was needed to proceed to the next development steps.