Commission approves $516,300 overrun for Mile 10 North expansion; city to pay half under interlocal agreement
Weslaco City Commission · June 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
Commission approved payment of $516,300 (city’s 50% share) to Hidalgo County Precinct 1 to cover right‑of‑way acquisition overruns on Mile 10 North expansion phase 3; staff said parcels increased from 44 to 105 and the overrun will be charged to the 2023 bond funds and budgeted going forward.
The Weslaco City Commission voted Tuesday to pay $516,300 as the city's 50% share of project overruns for the Mile 10 North expansion (phase 3), which staff said were driven by higher‑than‑expected right‑of‑way acquisition costs.
Staff explained the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans