Staff recommends $55,000 change order for resident observer services; contract award to Insight Pipe recommended
Summary
Staff recommended a $55,000 change order for KLH's resident-observer services on an interceptor rehabilitation project, citing high inspection costs; staff also recommended awarding the Gorehead Run interceptor rehabilitation contract to Insight Pipe Contracting through CoStar and releasing capital improvement funds.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Township staff on March 11 recommended authorizing a $55,000 change order to cover resident‑observer (RO) inspection services for the ongoing interceptor rehabilitation project and said the change order is needed because RO costs have exceeded initial allowances.
"We're gonna be recommending that we authorize a change order with KLH in the amount of $55,000 for the resident observer services for the project," staff said, adding that RO monthly costs have averaged about $12,000–$15,000 as contractors finish punch‑list work. Staff described earlier change‑order activity and asked council to consider the new request at the next meeting.
In a separate environmental‑services item staff recommended awarding the Gorehead Run interceptor rehabilitation contract to Insight Pipe Contracting through CoStar's cooperative purchasing program and releasing funds from the capital improvement fund; a memo dated March 2 (or March 4, transcript inconsistency) accompanies the recommendation.
Staff told council there remains a substantial surplus in bond funding for the project and that a $30,000 SCADA item included in the original contract will not be used, which helps offset the change‑order request. Council asked for a running total of change orders and a breakdown of where the project stands financially; staff agreed to provide an updated report.