Weslaco extends temporary moratorium on new duplex/triplex/fourplex and multifamily applications for 120 days
Summary
The Weslaco City Commission voted to extend a temporary moratorium 120 days to Sept. 16, 2025, to allow staff to review subdivision and zoning ordinances and complete capacity and impact studies; staff said exceptions and waivers are allowed and projects already vested or zoned will be grandfathered.
Get email alerts on the Land Use topic
No spam. Unsubscribe anytime.
The Weslaco City Commission on May 21 approved a 120‑day extension of a temporary moratorium on accepting new applications for duplexes, triplexes, fourplexes and other multifamily residential developments inside the city and within its extraterritorial jurisdiction. Staff said the extension will allow time to update the subdivision and zoning ordinances and complete necessary infrastructure impact and capacity studies.
Staff explained the moratorium (originally reissued in late 2024/early 2025 and reinitiated previously) covers all relevant permit and rezoning applications; property owners and developers may still apply for exceptions or waivers that will be presented to the commission for consideration. Projects already submitted before the moratorium or properties already zoned R2 remain grandfathered.
A staff member said work is under way on capacity studies for the South Wastewater Treatment Plant, drainage projects and related impact‑fee and zoning revisions. Commissioners approved the extension by voice vote; one commissioner recorded a nay but the motion carried.
Next steps: staff will continue work with consultants on ordinance and impact‑fee updates and present findings to the commission for further action during the 120‑day extension period.