Burleson council awards $1.48 million lift‑station rehabilitation contract

Burleson City Council · March 2, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council unanimously awarded a $1,346,208 construction contract to Dake Construction with an 8% contingency for a three‑lift‑station rehabilitation project, funding the $617,145 shortfall with transfers from sewer bond and rehab reserves; work is expected to proceed in April with a 60‑day schedule.

The Burleson City Council unanimously approved a contract to rehabilitate three aging lift stations, awarding Dake Construction the low bid of $1,346,208 and approving an 8% contingency of $134,620.80 for a total project authorization of $1,480,828.80.

Randy Morrison, the city's director of capital engineering, told the council the project was rebid after earlier attempts in 2024 failed to attract competitive offers. Morrison said staff identified a $617,145 shortfall and proposed transferring funds from sewer bond savings and other water‑and‑sewer rehab projects to close the gap. "We're proposing an 8% contingency on this project," he said, and added that the city expects to issue a notice to proceed in April and complete the 60‑calendar‑day contract by summer.

Council members asked staff about vetting the low bidder; Morrison said staff had contacted municipal references who provided positive recommendations. Following discussion, a motion to award the contract (mover: Victoria; second: Dan) passed unanimously.

The contract will be financed with identified sewer bond funds and transfers from related rehab projects, per staff presentation. Construction testing and quality‑control contracts will be issued to confirm delivery of the work.

Next steps: staff anticipates a notice to proceed in April and construction completion in roughly 60 calendar days.