Hurst City Council approves $1.82 million water-main replacement contract

Hurst City Council ยท February 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Hurst City Council authorized a $1,782,595 construction contract (plus $37,405 contingency) with 2R Construction LLC to replace aging water mains after recent winter-related breaks; the contract allows 270 calendar days for completion and passed unanimously.

The Hurst City Council voted to authorize the city manager to enter a contract with 2R Construction LLC for the 2025 miscellaneous water-main replacement project, approving a base contract of $1,782,595 with a $37,405 contingency for a total of $1,820,000 and a 270-calendar-day construction window.

Public Works Director Robert Salceda told the council the project replaces troublesome cast-iron and concrete lines with new PVC mains. "This project is to replace old troublesome cast iron lines and a concrete line that we have, with new plastic PVC water mains," Salceda said, noting one affected line on Cumberland experienced a water break in December and that the city received 11 bids for the combined work.

Council member Brotherton moved to authorize the contract; the motion was seconded and carried unanimously. The contract covers two streets where the city will replace two existing lines with new 12-inch mains, and staff said combining the two sites helped attract competitive bids.