Burlington staff outline scaled‑back Main Street Great Streets redesign, cite construction and utility challenges
Summary
City of Burlington staff said high bid costs reduced the Main Street Great Streets project area to Pine St.–South Winooski Ave; plans include parallel parking, wider sidewalks, protected bikeways and major underground utility work, with a contract end date of Nov. 1, 2026 and ongoing business outreach.
Get email alerts on the Burlington Main Street topic
No spam. Unsubscribe anytime.
Julia Ursaki and Maddy (Maddy) Suender, City of Burlington project staff, presented an update on the Main Street Great Streets project, explaining the city reduced the original scope and is focusing construction between Pine Street and South Winooski Avenue because of high construction bids. Ursaki described the design goals as providing a common downtown standard — "lighting, sidewalk widths, bike facilities, parking" — and said the redesign reallocates the public right of way to balance parking, pedestrian space, green space and bike infrastructure.
Suender gave a history of an aging ravine sewer that crosses the project area and said it carries combined stormwater and sewage. She described trenching and excavation challenges in constrained underground sections, showing photos of 30‑foot trenches and differences in historic sewer materials. Suender said the ravine sewer’s condition, and complex utilities generally, have constrained design and construction options.
Committee members raised business impacts and phasing. Sam Andersen said businesses have reported severe impacts and requested consideration of one‑way traffic to improve access; Ursaki and Suender said the contractor has adjusted sequencing and the contract end date remains November 1, 2026. Holly Francis asked about phasing; Ursaki described current Phase 1 as Pine St. to Winooski Ave and noted the city is seeking funding for subsequent phases, while Eleni Churchill asked about interim connectivity and striping to improve temporary bike connections.
City staff outlined their public outreach program — weekly emails, a project website, meetings with business owners, multilingual materials and a project hotline — and said detour and parking impacts are the primary concerns they continue to hear from businesses and the public.
No formal TAC action was taken on the Burlington Main Street project at the meeting.