Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
Rosenberg council approves multiple infrastructure projects, including Brazos Town Center connector
Summary
The Rosenberg City Council approved an interlocal agreement for the Brazos Town Center Connector and awarded construction bids for a 4th Street extension, a Public Services Complex recommendation, and a CenterPoint pole relocation to accommodate Coburn Road; funding came from county mobility funds, developers, RDC and voter-approved bonds as noted.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
The Rosenberg City Council on Jan. 6 approved a package of infrastructure actions intended to improve traffic flow and consolidate city services.
Council approved Resolution R-4015, authorizing an interlocal agreement with Fort Bend County for the Brazos Town Center Connector (Project No. 23419), a two-lane concrete roadway under I-69 to connect development on both sides of the freeway. Staff said engineering, design and construction costs are currently estimated at $1,244,000, with county mobility funds contributing up to $462,000 and the Rosenberg Development Corporation (RDC) contributing up to $925,000. Staff said design and engineering contracts will be executed first (estimated 90–120 days) with potential construction bidding and start by late summer.
Council then considered Resolution R-4007 to award bid No. 2026-02B for the 4th Street extension. Staff recommended awarding the contract to Untado Construction Company for $1,078,990.88 with a 90-calendar-day completion term. Funding will include 50% Fort Bend County mobility funds, 30% developer contributions and the remainder from the RDC; council approved the award.
On the Public Services Complex (Resolution R-3997), staff recommended awarding bid No. 2026-06B to Flinco LLC after interviews with the three lowest bidders. The item is funded by the 2023 bond proposition and the FY2024 capital improvement plan; staff recommended approval and the council approved the resolution. (The transcript lists a large numeric value that appears to be a transcription error; staff confirmed the recommendation to award to Flinco LLC but the accurate bid amount is not legible in the record provided.)
Council also approved Resolution R-4011 authorizing negotiation of a utility construction services agreement with CenterPoint Energy to remove Structure 05502 and install a new roughly 110-foot tangent pole to accommodate the future Coburn Road Segment 2. Staff estimated the relocation at about $287,000 and noted that CenterPoint would notify businesses and residents in the event of service interruptions.
All items were approved by recorded green/voice votes at the meeting; council discussion touched on construction timing, business access during work, scope of sidewalks (none planned in initial design for the connector) and safeguards to prevent use of general fund dollars.
