Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Council approves $237,500 change order for Kirkpatrick Drive Phase 2; contractor to get 15 extra days
Summary
Council authorized Change Order 1 for the Kirkpatrick Drive Phase 2 contract with Gilco Contracting Inc., adding $237,500 to cover roughly 12,500 additional cubic yards of excavation (at $19/yd3) and extending the contract by 15 days; the total contract is now $2,248,448, funded by the TERS program.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Weatherford City Council approved a $237,500 change order to the Gilco Contracting Inc. contract for the Kirkpatrick Drive Phase 2 extension, increasing the total contract to $2,248,448 and adding 15 days to the schedule.
Public Works Director Matt Ledpila said the contractor field-verified quantities after award and found excavation needs exceeded the original bid by approximately 12,500 cubic yards; the contractor agreed to honor the original bid price of $19 per cubic yard for that material. "As you can see at an increase of 12,500 cubic yards, the additional cost is $237,000," Ledpila said, and noted the revised contract days will total 285 days to completion. He also told council that additional excavated fill could be used on other city projects (for example, the new fire station) if suitable.
Council moved and approved the change order (motion by Eddie Wilder; second by Luke Williams). Staff said the project remains under the original estimated construction cost and that funding is provided under the city's TERS program. The transcript records the motion and its passage but does not include a vote tally.
