Weatherford utility director updates board on electric projects and meter upgrades
Summary
Director of Electric Utilities Joe Farley reported on about 29 electric projects, including overhead feeder upgrades, an overhead-to-underground conversion on Palapinto Street, a new main feed to Highway 51 to support development, and automated metering system base-station replacements costing under $200,000 and enabling roughly 1,000 new meters.
Get email alerts on the Electric Infrastructure topic
No spam. Unsubscribe anytime.
Joe Farley, Weatherford’s director of electric utilities, presented a broad update on roughly 29 projects covering planning, design, construction and recently completed work.
Farley described a 4,300-linear-foot overhead feeder project to improve three-phase service and to provide a feeder tie between the railroad substation and the Lake Weatherford substation. He also reviewed a Palapinto Street project that would convert about 6,500 linear feet of overhead lines to underground service and said the work will require coordination with AT&T, Spectrum and TxDOT. Several projects require joint agreements with Encore and other utilities, which Farley said can delay schedules.
On completed work, Farley pointed to a new main feed along Highway 51 (Beebe Fielder to Airport Road) to support nearby commercial development and future residential subdivisions. He noted this extension is sometimes joint-use with Encore and other providers.
Farley also explained that the automated metering base stations needed replacement after more than a decade of service. He told the board the three base-station replacements totaled “less than $200,000” and should provide another 10 to 15 years of reliable meter reads; he said the electric system will add about 1,000 customer meters over the next year.
Board members thanked Farley for the update and asked follow-up questions about service area lines and construction sequencing. No formal action was taken on these items at the meeting.