Facilities staff report progress on new elementary school and associated office renovations

Glades County School Board · April 28, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District facilities staff reported demolition of the old elementary interior, slab removal, removal of portables, ongoing inspections, start of drywall and expected furniture delivery mid-May; special facilities funding of $52,000,000 was cited as covering four project categories.

Facilities staff gave the board a progress update on the district’s new elementary school and related renovations. Staff said the older building interiors have been demolished, portables removed, and work is underway on the concrete slab; drywall has started and furniture deliveries are expected the third week of May with an informal target around May 15.

The presenter described planned security upgrades including swipe‑access electric gates with a video intercom for visitor screening, shelving and IT/textbook storage in the 9000 building, and punch‑list items such as playground drainage and a cafeteria freezer that is not cooling to below 28 degrees. Staff said warranty tickets are being submitted to construction vendors for outstanding items.

The presenter noted the district received $52,000,000 from the state allocated across four special facilities categories: the new school, transportation relocation, demolition of the old school, and renovation of office space. Staff emphasized that special facilities funds cannot be used for general salaries or benefits except for portions of staff paid directly by the special facilities program for oversight.

Board members requested a facilities walk‑through to review outstanding items and confirm warranty repairs. Staff said they will arrange the walk‑through and continue to submit tickets to the construction company for repairs.