Council informed of $116,919 change order at wastewater plant; work within loan contingency
Summary
Project staff reported silty soils under the aeration tank required excavation and stone replacement; the contractor moved forward and staff presented a $116,919 change order (less a $4,090 deduct), which officials said falls within the project's contingency of about $681,000.
Project staff updated the council on construction at the Oglesby wastewater treatment plant and described a site-specific issue that required a change to the aeration-tank foundation.
Ross Baker, a project representative, told the council the contractor encountered silty soil in about 10–20% of the tank footprint that posed a risk of differential settlement. Baker said geotechnical and structural teams…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat