Board approves $71,300 task order to design new box hangar; project estimated at $434,000

Hampton Regional Airport Board · April 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Hampton Regional Airport Board approved Task Order 23 — a $71,300 lump-sum fee for CHA to prepare design-build criteria and provide partial construction administration for a proposed 80-by-60 box hangar. Construction is estimated at about $434,000 and will use federal grant funding with a small local match.

The Hampton Regional Airport Board approved a $71,300 task order to produce design-build selection criteria and partial construction administration for a proposed box hangar north of the T-hangars.

A staff member presenting Task Order 23 said CHA’s lump-sum fee is $70,170 for labor plus $1,095 in expenses, totaling $71,300. The task order covers project management, grant administration with the FAA, solicitation documents, review of design-builder submittals, permitting and airspace analysis, and assistance in selecting the design builder.

The board was told the total construction cost is currently estimated at about $434,000 based on the concept plan. Staff explained the present grant year allows a higher federal share for the task order (noting 95% federal funding applies to certain 2025–2026 grant-eligible items) and that the local match on construction would be roughly 2.5% of the construction cost. A staff member summarized: “The total labor amount for this start covering this task order is, $70,170 plus an expense of $1,095 totaling up to a lump sum fee of, $71,300.”

Board members asked clarifying questions about scope and funding sequencing; staff explained later grants generally follow typical 90% federal / 5% state / 5% local patterns for construction grants outside the current eligibility window. A committee member moved to proceed and the motion was seconded; the board approved the task order by voice vote. The chair noted that signatures will be required to finalize the task order.

Next steps: staff will obtain the contractor’s final quantities to complete project closeout work and will proceed with the selection process for a design-builder under the approved task order.