Kent County approves $57,517 change order for biosolids expansion project

Kent County Levy Court · April 15, 2026

Summary

Levy Court approved Change Order #4 under Contract 2 for the biosolids capacity expansion project, a net increase of $57,517.04 for additional storm drainage piping and associated work; staff said project funds are available in the budget.

Kent County Levy Court approved Change Order #4 for the biosolids capacity expansion project on April 14, authorizing a net contract increase of $57,517.04 with M2 Construction for additional storm drainage piping, grading, roof drain piping and site restoration.

Staff told the court the additions total $120,817.04 and that an exterior building material change (from brick and block to colored architectural block) produced a credit of $63,300, yielding the net change order amount of $57,517.04. Staff confirmed sufficient funds are available in the project budget.

Commissioner Hertz moved to approve the change order and Commissioner Pepper seconded; the roll call vote was seven ayes. The president was authorized to sign the change order documents.

The project remains under the county's biosolids capacity expansion program and staff will oversee the work with the contractor.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source