Architects outline phased schedule for bond projects; board discusses CMAR and next steps

McPherson Unified School District Board of Education · March 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Contractors and architects presented a visioning and schematic design timeline for bond‑funded school construction; the board discussed CMAR procurement timing, phasing and potential summer work, with architects targeting schematic design completion in June and major high‑school construction beginning in February next year.

Presenters leading bond projects described a multi‑phase design and construction schedule for McPherson USD’s recently approved bond program.

Dwayne, the lead architect on the project, said teams have begun "visioning through schematic design" and are conducting building scans and stakeholder interviews. "Mobilization is happening right now this week," he said, and the team plans LIDAR scanning over spring break followed by staff visioning in March and April. Preliminary plans and adjacencies are expected in early April, exterior concepts in late April, and schematic design completion targeted for a June presentation.

Dustin (remote) summarized financing and timeline expectations, telling trustees that bond proceeds would be sold in early June with funds available by late June or early July to begin preconstruction activities. The presenters outlined a possible 18‑month construction period for the high‑school addition, with major construction kickoff in early February and completion phases stretching through 2028–29.

Board members discussed the advantages and procurement timing for a Construction Manager at Risk (CMAR). The architect recommended early CMAR engagement to inform constructability and procurement but acknowledged statutory processes for CMAR under Kansas law take six to eight weeks.

No formal board vote was taken on procurement method; facility committee review and a future request for board direction were the next steps.

Administration said it will share detailed schedules, financing plans, and RFP timelines with the board at the next meeting.