EDA and city staff outline Coliseum demolition, convention-hotel and GRTC transit-hub plan; committee forwards two redevelopment agreements

Finance and Economic Development Standing Committee, Richmond City Council · January 21, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Economic Development staff presented a phased city-center plan focused on Coliseum demolition (with potential underground parking), a convention-center hotel and a new GRTC transit hub; the committee voted to forward two related ordinances to council and asked for regular schedule updates on consultant findings and financing.

City economic-development officials told the Finance & Economic Development Standing Committee they are advancing two redevelopment agreements tied to the Coliseum parcel and a city-owned site at 500 North 10th Street as initial steps in a phased city-center redevelopment strategy.

Angie Rogers, director of the Department of Economic Development and executive director of the Economic Development Authority (EDA), described a three-piece approach: demolish the existing Coliseum while preserving foundation elements that could allow underground parking; kick off a first phase of vertical development including a convention-center hotel and associated parking; and develop a new Greater Richmond Transit Company (GRTC) transit hub integrated with mixed-use towers. "We are still following that vision," Rogers said, adding that staff are breaking the larger master plan into bite-sized, financeable projects.

Rogers cited prior Richmond Regional Tourism analysis estimating the city lost roughly $257 million in convention business between 2019 and 2024 because of limited nearby hotel capacity and said the EDA and GRECA (Greater Richmond Convention Center Authority) approved work by a consultant to study Coliseum demolition and related environmental factors. Dyrana Moore Clark, deputy director of the Department of Public Works, said the RFQ for the transit-hub parcel is active and responses are due this month; the hub vision includes 10 bus bays, a bus loop and pedestrian- and cyclist-focused access.

Committee members pressed for a financing strategy and a project schedule. Rogers and DPW staff proposed bi-monthly updates to the committee and said consultant cost and environmental assessments are still underway. "We want to make sure that we get to a viable financing strategy," Rogers said. The committee voted to forward the two ordinances (first amendment to the Coliseum Parcel Redevelopment Corporation agreement and a cooperation agreement for 500 North 10th Street) to council with a recommendation to approve.

The ordinances will be considered by full City Council as the city pursues consultant work, RFQ/RFP procurement steps and a financing approach; staff said federal partners and scheduled briefings will be solicited to align financing and timing.