EDA outlines RFQ/RFP timeline for Crawford Daysite; RFQ window closes May 7

Portsmouth Economic Development Authority · April 29, 2026

Loading...

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff said the Crawford Daysite RFQ closes May 7, with developer shortlisting by May 29, RFP issuance in June and a target council presentation by December 2026 to identify a development partner.

EDA staff reported progress on soliciting a development partner for the Crawford Daysite.

The Request for Qualifications was published March 4 and the RFQ window closes May 7. Staff said they have processed two rounds of questions through addenda and have observed interest from regional and Mid‑Atlantic developers; they expect to shortlist by May 29, issue an RFP to shortlisted teams in June and receive RFP responses by an August deadline, with a goal of presenting a recommended partner to city council around December 2026.

Board members asked whether interested parties were regional or national; staff said inquiries have come from regional, statewide and Mid‑Atlantic bidders and that a developer from outside the region could also respond. Staff characterized the timeline as aggressive but achievable and emphasized that next steps depend on the RFQ responses.