Justice Center project 87% complete after $1.8M payout, engineer says
Summary
John A. Hernandez reported the Justice Center construction is about 87% complete after an approximately $1.8 million monthly payout; elevators are being assembled, first-floor furniture installation is tentatively scheduled for May 19 and the third floor remains the project's critical path.
John A. Hernandez, P.E., the county project engineer, told the San Patricio County Commissioners Court that the Justice Center construction project is roughly 87% complete following an approximately $1.8 million progress payment this month. "The monthly payout for this month is approximately 1,800,000 and that'll bring…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat