Tuscarawas County authorizes bids for CR 62 bridge replacement over Tuscarawas River; recess held for Baltic well bid opening
Summary
The board approved advertising bids for the TUS-CR 62-0.70 bridge replacement and realignment over the Tuscarawas River at the request of County Engineer Doug Bachman, and recessed for a bid opening for the Village of Baltic Well Replacement Project; votes were 2–0 with one commissioner absent.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
On April 15 the Tuscarawas County Board of Commissioners approved advertisement for bids on the TUS-CR 62-0.70 complete bridge replacement and realignment of a deficient structure over the Tuscarawas River, at the request of County Engineer Doug Bachman.
The motion to advertise bids was moved by Commissioner Mitch Pace and seconded by Commissioner Kristin Zemis; the vote was Zemis yes, Pace yes, Greg Ress absent. The county did not provide estimated costs or a project timetable in the meeting transcript.
The board then recessed at 10:06 a.m. for the bid opening on the Village of Baltic Well Replacement Project and reconvened at 10:30 a.m. for the regular session. The transcript does not list bidders or award decisions; the action taken was to open bids and continue regular business after reconvening.
No additional engineering details or funding sources for CR 62 were provided in the recorded discussion.