Northborough creates rules for small data centers, caps new builds at 5 MW after robust debate

Apr 30, 2026

After lengthy questions about electricity, water, noise and security, the town approved a zoning amendment that defines data‑processing uses, excludes large data centers, and allows limited data‑center projects by special permit subject to seven infrastructure and compatibility criteria; a proposed amendment to reduce the cap to 2.5 MW failed.

The full story

Article 53 amended the zoning code to add a definition for data processing and record storage while distinguishing those uses from a data center. Planning‑board presenter Bill Pierce explained the intent: allow modest server/colocation reuse of industrial buildings while preventing large “hyperscale” installations by requiring special‑permit review and imposing a 5‑megawatt limit on new data centers.