Board awards middle-school gym HVAC contract to Casper's Construction after debate over local bids

Beatrice Board of Education (District 15) · March 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After discussion about local contracting and bid amounts, trustees rejected an initial low-bid recommendation and voted to award the HVAC installation at the middle-school gym to Casper's Construction with the mid-range bid; board discussed financing and summer timeline.

The Beatrice Board of Education awarded a contract for an HVAC system in the middle-school gym to Casper's Construction following a contested bidding process.

Board discussion outlined the procurement timeline: specifications were prepared after a site review, bids were advertised with a pre-bid meeting on Feb. 19 and sealed bids due March 5. Jason summarized that three contractors submitted bids ranging from about $308,006.33 (low) up to approximately $340,134.35 (high). The district’s initial recommendation to accept the low bid was not accepted; trustees expressed a preference to keep work local when feasible.

A subsequent motion to award the bid to Casper's Construction, the mid-range bidder (motion text in the meeting cited approximately $324,923), passed. Jason said the equipment and gas hookup costs were higher than originally estimated and recommended funding from a combination of building and general funds and possibly depreciation funds; he also said work is planned to begin after school dismisses and to be substantially complete by mid‑July, noting that summer gym availability will be affected.

Why it matters: the project brings permanent air conditioning to the middle-school gym for the first time and requires coordination with summer activities and local subcontractors.

What’s next: staff will finalize contract paperwork, coordinate subcontracting and notify user groups about summer impacts.