White House board approves multiple service and infrastructure contracts; projects include janitorial, parks shade, sewer repairs and force main work

Board of Mayor and Aldermen, City of White House, Tennessee · January 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board of Mayor and Aldermen cleared several contracts by voice vote: janitorial services ($88,876.32), a shade structure for tennis courts ($46,968.63, 50% grant reimbursement), a cure-in-place pipe lining authorization (up to $100,000), Southern Force Main Phase 6 ($636,706) and CSR task orders for Calista Road ($40,900).

At its January meeting the White House Board of Mayor and Aldermen approved a package of procurement and construction items affecting city facilities, parks and wastewater infrastructure.

Janitorial services: The board authorized the City Administrator to contract with Janney King for janitorial services at city facilities in the amount of $88,876.32, with services beginning March 1, 2026. Staff said the contract was rebid after adding the recreation center to the scope; a five-person evaluation committee ranked Janney King the top scorer. Council discussed occasional missed areas and how deep-cleaning or special services would be handled; staff said some items are available at additional cost. The motion carried by voice vote. (Transcript includes variant spellings of the vendor.)

Parks shade structure: Parks and Recreation Director Kevin Whitaker presented a grant-supported purchase and installation of a shade structure and 12 benches for the tennis courts from Mid South Recreation Inc., contract amount $46,968.63. Whitaker said the grant will reimburse 50% of the cost; benches are on order and the vendor quoted about 12 weeks to complete the project. Council asked about durability and replacement costs; Whitaker said the fabric carries a 10-year manufacturer's warranty and that similar installations in parks have lasted multiple years. The motion carried.

Wastewater repairs and projects: Wastewater Director Travis Garman briefed the board on a planned cure-in-place pipe lining procurement (unit-price bid) to address separated and cracked pipes and reduce infiltration/inflow (I&I). The authorization to contract with BLD Services LLC was capped at $100,000; Garman said the funding should enable roughly 20–25 repairs depending on footage and incidental needs. The board approved the authorization by voice vote.

Southern Force Main Phase 6: Garman presented a low bid award to Cumberland Pipeline LLC in the amount of $636,706 for Phase 6 of the Southern Force Main replacement, describing a route from the former cul-de-sac (now roundabout) on Cedarbrook Drive to Tyree Springs Road using HDPE material consistent with earlier phases. Garman emphasized this is a like-for-like replacement, not a capacity increase. The motion carried.

Calista Road deconfliction: The board authorized City Administrator to contract with CSR Engineering for task orders related to Calista Road Phase 1 sewer deconfliction for $40,900. Garman said engineers identified a roughly 800-foot stretch of 12-inch pipe that must be moved to avoid conflict with a road widening project; he said existing easements likely cover the work and that bypass and grinder-pump strategies will maintain service during tie-ins. The motion carried.

Most approvals were recorded as voice votes with "Aye" and the transcript does not include individual roll-call tallies. Staff will proceed to execute contracts and return with scheduling or budgetary implications as needed.