Board awards $185,000 bid for concrete pad for new public service storage building

Board of Mayor and Aldermen · November 20, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a $185,000 bid from All Things Outdoor Concrete Inc. to construct an 8-inch, 14,000-sq-ft concrete pad (70x200 building footprint) for a public service storage building; Public Services Director Isaiah Manfredi described the 5,000-psi mix, 3/8-inch rebar and subbase specifications and explained the need to protect equipment from corrosion.

The White House Board of Mayor and Aldermen approved awarding a $185,000 contract to All Things Outdoor Concrete Inc. to construct a concrete pad for a planned public service storage building. Public Services Director Isaiah Manfredi described the project and recommended award after a bid process that produced five bids.

Manfredi said the concrete pad supports a planned 14,000-square-foot storage building (approximately 70 by 200 feet). He described construction specifications: an 8-inch-thick concrete pad with fiber mesh and entrained air, a 5,000-psi concrete mix, 3/8-inch rebar reinforcement, 4–6 inches of 57 stone subbase, and measures to prevent moisture intrusion. Manfredi noted the city has significant heavy equipment (including a $217,000 MowerMax) that needs indoor storage to slow corrosion from naturally occurring H2S and weather exposure.

Board members asked whether the selected contractor had demonstrable commercial experience; Manfredi said the contractor indicated work on large residential and some commercial projects and that bid specifications were industry standard. After discussion the board moved and carried a motion to approve the bid award.

The contract award covers only the concrete pad portion; the building will be bid separately and the larger CIP budget for the project was referenced during discussion.