Board approves construction manager at risk, advances CTE high school GMP amid value‑engineering caveats
Summary
Ector County ISD trustees approved proceeding with a construction manager at risk and accepted a guaranteed maximum price (GMP) for the new Career & Technical Education high school after staff said the delivered number was slightly higher than expected but likely reducible through value engineering.
Get email alerts on the Bond Program topic
No spam. Unsubscribe anytime.
Ector County ISD trustees on May 20 approved moving forward with a construction manager at risk and accepted a guaranteed maximum price for the district's new Career & Technical Education (CTE) high school, a major milestone in the Bond 2023 program.
The superintendent and staff presented the GMP package to the board and said the GMP was delivered May 15. Staff said the number was “slightly higher than we did anticipate” but added they expect to reduce the total through design value engineering and continued pricing negotiations. The board voted to approve proceeding with the construction manager at risk selection and related preparations to issue a purchase order.
Why it matters: the CTE building is a cornerstone project of Bond 2023 and will house career-technical classrooms and competition gym facilities. Approving the construction manager at risk lets the district lock in contracting strategy, begin detailed scheduling and continue site work while staff refines costs.
Details presented by staff included the recent delivery of the GMP, ongoing block and steel erection at other projects to demonstrate construction progress, and an estimate that some line items—such as the fully stocked culinary arts kitchen—contributed to the higher price. Staff told trustees they had identified potential value‑engineering areas and expected the GMP to come down “considerably” as work proceeds.
Board action: a motion to approve the construction manager at risk and accept the GMP was made, seconded and carried. Trustees were offered an opportunity to discuss procurement strategy and cost-control measures before voting.
Next steps: staff said the district will proceed with contract documentation and that a tentative groundbreaking for the CTE building is scheduled for June 17. The board will continue to receive updates as value‑engineering and final pricing occur.