Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

LAWA hears construction progress and McCluskey Canal water-quality pilot findings

Lake Agassiz Water Authority (LAWA) Board · March 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board received construction and McCluskey Canal updates: contractors may begin pipe installation as frost allows, 59 miles under contract with 30 miles in the ground, a target of ~14 miles to be installed this year; pilot water-quality testing showed poorer quality near the canal intake, increasing treatment needs and informing design work.

LAWA board members on March 27 received updates on construction progress and on pilot testing related to the McCluskey Canal and the planned biota water treatment plant.

A construction presenter said contractors have been preparing materials and planners are aiming to put about 14 miles of pipe in the ground this season if frost conditions permit. The presenter reported 59 miles of pipe are either under contract or…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans