Council authorizes ODOT-led agreement for Loveland Madera Road Phase 2; USPS right-of-way issue could push project to 2028
Summary
The council voted 7–0 to authorize an ODOT Local Public Agency agreement for the Loveland Madera Road Phase 2 project. Staff said the project’s scope is about $6.2 million with a federal cap near $4.6 million, leaving roughly a $2.0 million local gap that may be largely covered by OPWC funding; a right-of-way matter with the U.S. Postal Service may delay the project until 2028.
The Loveland City Council unanimously approved a resolution to authorize the city manager to execute an ODOT-led Local Public Agency (LPA) agreement for the Loveland Madera Road Phase 2 project.
Staff described the project scope as originally estimated around $6.2 million with a federal funding cap of about $4.6 million, leaving an approximate $2.0 million shortfall for which staff has applied for OPWC funding. Staff reported that OPWC…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat